The Suez Canal Bridge Project in Egypt :the First Crane of its Steel Structure Has Been Successfully Completed.
发布时间:2020-01-17 人点击

图片1.jpg

On January 15, the first crane of the steel structure of the Suez Canal bridge project inEgyptwas successfully completed. Witnessed by the General Tarek of GOE, consulting companies and third-party inspection companies, the first 70-ton steel structure of the bridge floor was slowly raised and accurately lowered.

  

Early-Stage Preparations

Since the first batch of 7145-ton steel structure arrived at the PORT SAID EAST in the Egyptian Mediterranean on December 24, 2019, as planned, the joint project department has sent personnel to actively communicate with the customs, quickly complete customs clearance, and transfer the steel structure to the construction site safely and timely.

 


The Control Process

In order to ensure the successful completion of the first crane installation of the steel structure, the joint project department planned in advance and carefully deployed, and did enough work in the field of safe and civilized construction, construction technology disclosure, quality acceptance, organization and other aspects of the division of labor.

图片2.jpg

The successful completion of the first crane marked the official start of the steel structure installation of the The Suez Canal Bridge Project inEgypt and began a new journey of the project in 2020.

图片3.jpg